Abington to Advertise Hearing for $3M in Bonds

Is your street on the list of projects?

 

 

The Abington Public Works Committee on Monday approved a motion to advertise an ordinance for the issuance of $3 million in general obligation bonds for public hearing on March 8.

The Board of Commissioners meeting is Feb. 9.

According to a memo in the agenda, the Abington Board of Commissioners adopted a 2012 budget that included provisions for increased debt service for township-wide drainage projects.

See the drainage projects below.

Abington Township Manager Michael LeFevre said the township’s budget originally called for $2.7 million in bonds in 2012; township engineer Michael Powers said he felt “more comfortable” with the $3 million figure given the projects on tap.

LeFevre said because interest rates have declined in recent months, the extra $300,000 wouldn’t affect the debt service.

About $29,000 will be deducted from the bond proceeds: About $12,000 for a financial advisor (Gordon Walker of PFM); and between $15,000 and $17,000 for bond council (Liz Preate Havey of Pepper Hamilton). 

 

East Side Projects, 2012 Bond Issue

Location Project Cost  Ward
1665 Susquehanna Road Bypass Pipe $68 K 1
1707 Hampton Road New Storm Sewer 40 K 1
1100 block of Lindsay Lane New Storm Sewer 60 K 1
1331 Meadowbrook Court Creek Bank Stabilization 20 K 1
962 Susquehanna Road New Storm Sewer 60 K 2
300 block of Cadwalader Avenue New Storm Sewer 40 K 3
Rossiter/Thomson/Coolidge New Storm Sewer 160 K 5
972 Rydal Road Replace Existing Storm Sewer 120 K 7
2900-3000 block Old Wesh Road Replace Existing Storm Sewer 80 K 8
2884-2888 Senak Ave. Storm Sewer 20 K 8
2920 Rossiter Ave. Yard Drain 12 K 8
Thunderhead and Blue Jay roads New Inlets 40 K 8
1400 block of Lindbergh Avenue New Storm Sewer 140 K 8
Cleveland Avenue Storm Sewer/Yard Inlets 40 K 10
2421 Pershing Ave. Yard Drain 20 K 14
1200 block of Johnston Avenue Replace Existing R/R ties 150 K 15
1100 block of Johnston Avenue Replace Existing R/R ties 150 K 15
Woodland Road, High to Arline avenues Storm Sewer 120 K 15
St. Charles Yard Drains/Sump Pumps 60 K  15
Total - $1.4 million -

 

West Side Projects, 2012 Bond Issue

Location  Project Cost Ward
2700 block of Jenkintown Road New Inlets $20 K 6
100-200 Blocks of Central Avenue Storm Sewer 160 K 6
430 Central Ave. Storm Sewer 160 K 6
Houston Avenue/Railroad  New Storm Sewer 40 K  6
2809-2811 Mount Carmel Ave. New Yard Drains 20 K 6
305 Elm Ave. Yard Drain 20 K 6
700 Bock Penn/Garfield/Tennis avenues New Storm Sewers 240 K 9
Penn/Garfield/Tennis avenues Storm Sewer 120 K 9
Highland Avenue to Cantebury Creek Bank Stabilization 120 K 11
552 Baeder Road Storm Sewer 120 K 11
Baeder Creek/Crescent Avenue Creek Bank Stabilization 60 K 12
Weldon to Elk avenues New Storm Pipe 140 K 13
300 block of Cliveden Avenue New Storm Sewer 140 K 13
400 block of Linden Avenue New Storm Sewer 80 K 13
400 block of Sylvania/Geneva/Easton New Storm Sewer 160 K 13
Total - $1.6 million -
Related Topics: Abington Bond, Bond Issue, and Flooding

Victor B. Krievins

6:52 am on Thursday, February 2, 2012

This Bond Issue is needed but the $29.000.00 of related expenses seem a bit excessive.